Record of Monthly Generation (kWh)

The table below is a record of the units of electricity generated each month since the Hydro was commissioned.

10% (approx.) of the electricity is supplied to Bridge End Mill and the remaining 90% (approx.) is supplied to the National Grid.

NOTES

May'10, Jun'10, Sep'14, Jul'15: No generation due to a prolonged period of low river level

Dec 2013 to Apr'14: No generation due to a prolonged breakdown due to failed lower bearing

Aug'15: Generation restricted during installation of new Variable Speed Control System

May'18, Jun'18, Jul'18, Apr'20, May'20, Jun'20, Apr'21, Jun'21, Jun'22: Low generation due to very low rainfall